11 March 2010 SH25 Te Puru Bridge Restriction
At Te Puru township - north of Thames on SH25 half of the old bridge has been demolished to allow a new bridge to be constructed in stages replacing the old bridge. Traffic is currently running over the remaining half of the old bridge. On Monday this week 4 new beams were placed to form part of the new bridge and because these are much higher than the old bridge they create a lane width restriction that may affect trucks and trailers with over-dimension loads.
The width currently available across the bridge is 3.5m which is the normal lane width on our State Highways. It is expected that this situation will only continue till the end of April when traffic will be diverted onto the new half of the bridge.
10 March 2010 SH1 Taupo - Resealing Works at Night
Opus have advised of resealing works at various locations on SH1 in the Taupo area at night. These are changes to previously advised dates:
- Wednesday 10 March: Bulli Point
- Sunday 14 - Tuesday 16 March: Poihippi Rd - Huka Falls lookout
8 March 2010 SH1 Auckland Harbour Bridge - Police Escorts
This applies to all Northbound Loads from and including March 21st 2010 until further notice.
All "OVERSIZE" loads requiring a Police escort (phone *555) for NORTH BOUND TRAVEL are to wait in the bus lane opposite the Caltex Service Station in Fanshawe St. Please have consideration for buses requiring to uplift passengers from the adjacent stop. Fletcher Construction will be placing concrete barriers in the left lane of where we currently wait as a precursor to carrying out works associated with the new Vic-Park tunnel. DO NOT ENTER the Fanshawe St onramp under Vic-Park flyover without your Police escort!
South bound travel is not affected.
9 February 2010 SH3 & 4 Various Wanganui Construction Sites
Putiki Roundabout (SH3/4)
Transport though north and south is currently good with no work on SH3. SH4 Anzac parade is being worked on with drainage being installed. The road width is generally ok for normal traffic and narrower transporters/ loads. For extra wide loads ie; houses in and out of SH4 / Wanganui East area, should use the southbound slip road which will necessitate some good traffic management if used during the daytime when heading into Wanganui East (One way)
B Bullock is the contractor, STMS is Ivan Bullock Ph. 027 2555723.
SH4 Anzac Parade
There is river bank reconstruction work adjacent to the town bridge, this is generally 2 lane but can be reduced to 1 lane at times during the day. This road works will accommodate approx. 8 metres outside normal work hours.
I D Loader is the contractor, STMS is Ian Loader Jnr. Ph. 06 3489034 bussiness hrs. Ask for Ians number.
Carlton Ave, SH3
If you are over 2.5 wide DO NOT GO THERE. This section of road from Liffiton St to Smithfield Rd is currently having major pipe laying down the full length of the road plus the new roundabout constructed, and will probably be restricted to normal width vehicles for quite some time.
Currently you cannot even get an empty 3.1 transporter through the proliferation of cones etc. HEB is the main contractor with others. STMS contact is Nick on 027 2840397.
Use Heads Rd, Mosston Rd, Montgomery Rd. to and from SH3, and this will take approx 9m wide.
Big overweights should check with NZTA Wanganui for availability of this route. (Note: Montgomery Rd has quite a steep hill at the top end, if you prefer a flatter route, use Mosston Rd, Tayforth Rd, Rapanui Rd coming out adjacent to Westmere Service Stn. (BP). This will take approx 10.5m. Tayforth and Montgomery Rds both turn off Mosston Rd 50 yds apart.)
Carlton Ave / London St Roundabout
Work has started on this upgrade and at present has no difficulties as the contractors are widening Fitzherbert Ave / London St corner and are working clear of the roadway, London St now has a traffic island installed, currently without signs, there will be no significant width problem here as it is still wider than the road and signs etc at the bottom of St Johns Hill / Victoria Ave Intersection.
I D Loader is the contractor Ph. 06 3489034 bussiness hrs.
Our local eye in the sky (Pilot: Adrian Flett) will keep us posted on developments with all these projects on these important heavy haul routes
1 February 2010 SH1 Levin - Waiauti Bridge Replacement
GHD Ltd have advised of works to contruct a new bridge at Waiauti, some 14km south of Levin. Due to the tight nature of the construction site, work on both the new bridge and work to demolish the old bridge will be occurring at the same time. This will result in pavement and load width restrictions as one lane on each bridge will be used for a period of time and work equipment may be close to the roadway.
Due to this a notification process will be put in place for overwidth loads and some overweight loads to ensure that passage is available at the worksite. The exact work timetable is being formualted at present, but it is likely that some restrictions are likely to be commencing in around 2 weeks time.
Further information will be provided as it comes to hand.